Armed with Production Sharing
Contracts (PSC) with the Government
of India,Reliance Industries
Limited (RIL) recently sold 30 percent of
its stake in East Coast oil and gas fields to
the overseas giant British Petroleumfor a
whopping $7.2 billion. The development
has much in-between-the-lines to be inferred.
The company has realised a staggering
$7.2 billion from the deal but the
Government of India, the real owner of
the resource, stands as a loserwith ameagre
Rs.267 crores as ‘profit petroleum’ as
its share in its treasury.On posing the question howmuch the Reliance has earned from the project so far, Ministry officials told Bureaucracy Today that they do not know the exact number. It is intriguing that the Government is not keeping a tab as to howmuch the Reliance has earned fromthe production in KG-D6 Block since April 2009. No wonder it has run out of numbers to configure the loss it has suffered till now.
It may be recalled that the RIL had initially placed a field development plan (FDP) to produce 40 million standard cubic metres per day (mmscmd) of gas. The expenditure was pegged at $2.47 billion. Later the RIL submitted a renewed field development plan claiming that it would produce 80 mmscmd at the expense of $8.84 billion. It is only after the RIL realizes this $8.84 billion that the Government of India will start getting its share of profit petroleum. Tapan Sen, Member of Parliament and Member of the Standing Committee on Petroleum and Natural Gas, points out that the RIL has already realised $7.2 billion out of the $8.84 billion. Why can’t the Government take steps to claim profit petroleum and ascertain the time period within which the RIL will pull in the remaining $ 1.64 billion so that the Government share in profit petroleum may increase?
The renewed field development plan worth $8.84 billion was approved by the Ministry of Petroleum and Natural Gas in 33 days. Those were the golden days for Reliance as Murli Deora was the Petroleum Minister. Times and Ministers have changed since then.
CHANGE IN CIRCUMSTANCES
Even as the Ministry of Petroleum and
Natural Gas’ growing impatience is evident
from the fact that it is now mulling
over ways to restrict the RIL from realizing
its costs incurred in the development and
operation of KG-D6 Block, industry experts
say they fail to understand as to why
the Government failed then to take legal
action against the company. Even before
the Government could plan to do anything
legally to save its interests in KG-D6 Block,
the RIL has gone de jure by slapping the arbitration
notice on the Government. The
Government has sought time till January
31, 2012 to reply to the notice. The notice
came after the Government made its intention
clear on disallowing the RIL from recouping
the expenditure incurred in
constructing production and processing facilities
at D-1 and D-3 gas fields in D6 Block.
The trouble for the RIL started after
reports of a drastic production fall in D6
Block from the usual 60 mmscmd to 40
mmscmd. It may be noted that the aggressive
field development plan supported by
the DGH, was approved during Murli
Deora’s tenure as Petroleum Minister for
80 mmscmd. The RIL was to produce 61.88 mmscmd of gas from 22 wells by April
last year and 80 mmscmd from 31 wells
by 2012.On November 22, Petroleum Secretary GC Chaturvedi said the Petroleum Ministry would decide within 3-4 weeks on the action to be taken against Reliance Industries for its gas output falling below the target from the East Coast fields. The Secretary had said: “We had sought the views of the Law Ministry. Our Ministry is now examining their views. In the next three-four weeks, we will be able to decide on the future course of action.” On December 25, the Ministry of PetroleumandNaturalGas told the Parliamentary Committee that the Production Sharing Contract (PSC) for the block “does not provide for penalty” in case of a shortfall in production targets. Parliamentary CommitteeMember Tapan Sen in an interviewwith this publication expresses concern that the Production Sharing Contract (PSC) for the block “does not provide for penalty” taking the shortfall in production targets as a breach of the contract.According to the Ministry, it can only do so in an event when it ascertains that the RIL has not dug the committed number of wells.Bureaucracy Today learnt fromMinistry officials that the aspect is still being looked into but it feels the 40 per cent drop in the outputwas because the company had left the wells underutilized.
A Ministry source on condition of anonymity says, “The possibility that the entire KG-D6 block is not covered by an adequate number of wells cannot be ruled out because of which the productionmay showa downward trend.” This point has also been raised by the Comptroller and Auditor General in the performance audit of the PSCs. According to a Ministry source, “the Government of India is getting a raw deal in KG-D6 Block. It is due to numerous compromises made at various stages which have now accumulated to such an insecure position for the government.”



